I.E department law


I.E department law 
Tex-know
Now we know about same law for using garments I.E department  :s
·        SMV= basic time +(basic time × allowance)
·        Basic time = Observed time ×rating time
·        Observed time =  total cycle time ÷ No of cycle
·        Earn minute = No of pc’s production × garments SMV  
·        Capacity = 60÷  capacity time in minute
·        Cycle time = 60 ÷team target
·        Daily output =  working hour ÷SMV
·        GSD = ( man power × working hour ) ÷ target
·        Standard Pitch Time (SPT) = basic pitch time + allow %
 
·       Factory capacity = ( working hour ÷ SMV ) × total worker ×working day × Efficiency     
·        Efficiency =(earn min × available min) ×100 